Building Home Update 08

February 7, 2026

Building Home Project Update

Since our last update, we have seen incredible progress on our new church home. We are grateful that the favorable fall weather allowed us to make up for earlier delays and complete much of the building’s exterior envelope. The roof is now finished, meaning the building is officially "in the dry!"

With the mild start to winter, the exterior brickwork is also complete. You may notice some variation in the brick colors right now—don't worry, this is intentional! As part of the final design, all exterior brick will be painted this coming spring.

Permanent windows and doors are scheduled for installation very soon. In the meantime, openings have been temporarily sealed to allow for interior heating. This has enabled our teams to make significant headway inside, including:

Foundation & Framing: Underground plumbing and concrete flooring were completed early in the winter, and all interior walls are now framed.

Systems: Mechanical and electrical work is well underway, including ceiling ductwork, wall wiring, and fire protection systems.

Finishing: Drywall installation has begun on several interior walls, and large equipment like AC units and electrical panels will be installed shortly.


It is inspiring to see these spaces take shape. From the layout of the worship center to the children’s wing and the Dream Team Center, the vision is becoming a reality. God is good, and we look forward with great anticipation to how these spaces will be used for His glory!